News Flash

ET - CIP Current Capital Improvement Projects

Posted on: December 5, 2022

Water Pollution Control Plant Secondary Effluent Line Rehabilitation

WPCP Simultaneous Service During Bypass Line Installation

The Secondary Effluent line is at the core of necessary decontamination processes at the plant. Notice to Proceed construction was given on August 2022. 

The line will be rehabilitated using Cast in Place Pipe (CIPP), that allows for reliable and expedient work so the plant can resume continuous regular operation. Additions to the project include an access vault to the line and miscellaneous repairs of related apparatuses.

The project falls under our Capital Improvements Projects. This project has an estimated 90 working days of completion, and a budget just under $1 Million.

This project is expected to be completed by December 2022.

WPCP Secondary Effluent Line Rehabilitation (PDF)