When are plans or design drawings required for a construction permit?

Typically, plans, specifications, energy calculations, soils reports and other data are required whenever new construction work is proposed. The documentation is reviewed by all pertinent City departments to ensure compliance with applicable codes and regulations before building permits are issued. Permit applicants should allow between 5 to 20 working days, depending on the complexity of the project, for initial plan review activities to be performed. In order to provide fast and efficient plan review services, we utilize in-house personnel as well as consultant agencies. Call us at 510-577-3405 for help in reviewing what information you will need for your project.